BBMP’s rainwater harvesting works stillborn

The city council allocated crores of rupees last year for rainwater harvesting at parks, playgrounds and BBMP buildings. What happened?

The monsoon rains are delayed this year. But by sheer coincidence, BBMP’s rainwater harvesting plans of last year remain unimplemented, almost as if the monsoons were granting their own extension to BBMP, ominously. What’s worse, a Citizen Matters inquiry revealed that the city’s accounts department declined to release funds due to the engineers’ lack of interest.

Bengaluru faces a shortage of 410 MLD (megalitre water per day) of water. The average rainfall here is 923 mms within a geographical area of 800 sq kms.  It is in this context by seeing the potential of RWH, BBMP made implementation of rainwater harvesting compulsory in all its offices, parks and playgrounds and allocated Rs 20 crores in 2011-12 budget. It also proposed to reserve 10 per cent of ward grant allocation to RWH. In addition to that, to encourage citizens, a two percent rebate in property tax also proposed in all the houses, which are having RWH units. This 2011-12 decision now seems utopia.

A BBMP official explaining how the newly installed RWH unit works.

Last month, when Citizen Matters spoke to Krishnaswamy K S, Executive Engineer of the RWH project, ahead of the nearly approaching monsoon season, he said, “We have not done any kind of works associated with RWH so far. But we have some plans and have started doing some work.” 

There is more. The 20 crore rupees allocated in the previous budget for RWH has been withheld by the BBMP Account Section due to the lackadaisical approach from the incharge engineers. The officers in-charge for RWH were supposed to submit the proposal details prior to the release of the money.

“The in-charge officers were supposed to do the site verification, tender allocation, project layout and so many other works prior to the release of the money. Nothing has been done so far. So the money has not been released,” said N V Subbanna, Chief Accounting officer BBMP.

B S Prasad, Chief Engineer for RWH at BBMP, declined to comment on the delay.

In the meantime, a new financial year has begun and the budgetary allocation of the previous year appears to have been forgotten.  Most of the flats, parks, playgrounds, offices, buildings in the city are still devoid of a RWH system.

RWH unit at BBMP head office is the biggest one.

Ironically, one RWH unit was installed at BBMP head office and at IPP (Indian Population Programme) Malleswaram office this year. Surprisingly, this project was not part of the BBMP RWH initiative. Executive Engineer L Chandrasekhar says, “The total cost of the project was Rs 35 lakhs. We have done all the works with our department money only. It does not have any connection with the 20 crore allocated for RWH in the budget.”

As our officials take a long stretch to plan and blame each other for the delay in starting the work, even the delayed monsoon rains may come and go. The city’s water problem will only be more severe in the coming days.

Comments:

  1. Shashidhar K. G. says:

    BBMP projects (east) have implemented two recharge wells in Richards Park (ward60) in 2011.This was an initiative of RTRA with the support of the local MLA Hon Prasanna Kumar.

    Shashidhar /RTRA-Richards Town Residents Association

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Scorched cities: Documenting the intense Indian summer of 2024 

Here is a round up of how the heat wave has impacted cities across the country and the measures being taken to combat it.

Summer in India has been abnormally hot this year and will continue to be so till June 2024, warns the India Meteorological Department (IMD). As reported by The Wire, in a virtual press conference on April 1st, IMD director general Mrutyunjay Mohapatra said that in the months from April till June, most of India will witness temperatures above normal. IMD's caution comes at a time when the UN’s World Meteorological Organisation also recently warned that 2024 will likely face worse summers after global heat records across the world.  “During the 2024 hot weather season [April to June (AMJ)], above-normal maximum…

Similar Story

The trials of being an urban farmer in Delhi’s Yamuna floodplains

Agriculture around the Yamuna is strictly prohibited due to river pollution concerns, but where does that leave the farmers?

The river Yamuna enters Delhi from a village called Palla and travels for about 48 km. There is a part of the river, approximately 22 km long, between Wazirabad and Okhla, which is severely polluted, but for the remaining 26 km of its course, the river is still fairly clean. The surroundings serve as a habitat for a large number of trees, flowers, farms, birds, and people who have been living here for as long as they can remember. They are the urban farmers of Delhi-NCR, and they provide grains and vegetables for people living in the city. Although farming…