BBMP pours 90 lakhs down the incomplete drain

Bangalore has a population of nearly 9 million. These contractors managed to take one rupee from every Bangalorean for the work that was not even completed. BBMP officials connived to make extra payments on rajakaluve works that CAG says was never done.

CAG (Comptroller and Auditor General of India) has unearthed yet another BBMP scam. This time it is about the excess payment of over Rs 90 lakhs paid to two contractors for drain de-silting works in 2009. Despite spending 1.65 crore rupees on these two rajakaluves, it is not clear how much work was actually done, as BBMP officials had manipulated the work records. This has come out in the 2008-10 audit of BBMP by CAG.

Rajakaluve works in another area. File Pic: Anisha Nair

The irregularities were on de-silting and re-sectioning two rajakaluves (major Storm Water Drains or SWDs). One rajakaluve connected Attur lake to Yelahanka Puttenahalli lake, and Yelahanka-Jakkur-Rachenahalli lakes. The second one connected Rachenahalli lake, Mariyannana Palya SWD, Byatarayanapura village, Amruthahalli lake, Allalasandra lake and Jakkur lake.

Tenders were not called

According to the Karnataka Transparency in Public Procurements Act, 1999, tenders have to be called for such works. But in August 2008, the then-BBMP Commissioner S Subramanya requested state government to exempt these two works from the Act, saying that the works were urgent and that there was no time to invite tenders. Government allowed the exemption.

How they fudged figures

What followed was manipulation of work estimates and records. The Executive Engineer (EE) of SWD, Hebbal valley, who had awarded the works, had inflated the estimated rates. For works not awarded by tenders, rates are fixed based on Schedule of Rates (SR) specified by the state government.

In this case, rates of PWD, Bangalore Circle was adopted. The proposed work – removing silt and depositing it in layers on sides of the SWD – was not mentioned in PWD’s list. But according to the rules they could adopt the rates from another department which had similar work listed. In this case it was listed under Minor Irrigation department, which gives the rate of Rs 51 per cubic metre (cum).

EE instead adopted the PWD SR specification for a completely different work – excavation of foundation trenches for culverts. Estimate for this work is Rs 88.70 per cum.

Another 26% was added to this amount, making the total Rs 112.82 per cum – more than double the actual amount. The additional 26% was for ‘foul work conditions’, even though the canal carried only extra lake water and not sewage. Besides, the PWD rates do not sanction such extra payment.

Chief Engineer of SWD gave technical approval to these estimates. With the inflated rates, the combined estimated cost for the works was Rs 3.13 cr. As of December 2009, Rs 1.65 cr had been paid to the contractors for excavation of 1.46 lakh cum. BBMP’s loss because of inflated estimate was over Rs 90 lakhs.

There was no urgency

The argument that the works were urgent was also moot, as BBMP proceeded very slowly after getting the government exemption in August 2008. It was almost a year later, only in July 2009, that SWD department got BBMP Administrator Dilip Rau’s final approval for the works. (Decision making was done by the Administrator at the time as there was no elected Council.)

CAG report says that while giving approval, Rau had observed that the delay in starting works defeated the purpose of exemption. Tenders should have been called during the period of delay so that works could be given at lower amounts, he had said.

Despite all this work was incomplete

The report also raises doubts on whether the work was completed at all, since documents related to it had been manipulated. For instance, the EE had awarded works to the contractors in January 2009, even before getting CE’s and Administrator’s sanctions, and before making terms of entrustment (conditions set for taking up work). But EE’s checklist mentions that one of the two works had started in November 2008 itself.

No proof of completion of work

Contractors have to submit photos showing progress of work while submitting bills to BBMP for reimbursement. The photos they have submitted were also dated November 2008; these were of distant pictures of a stationery excavator.

Dates of work fudged too

Also, before de-silting work starts, measurements have to be taken so that extent of work done can be determined. Here, these pre-measurements are dated April and July 2009 for the two works, even though work was happening in November 2008.

CAG says that since pre-measurement records are not valid, it is not clear if the work was done at all. It recommends a detailed investigation on the issue. Though CAG had written to the state government in January 2011, it had not got any reply as of March 2011.

Comments:

  1. mohammed says:

    Dear sir, your find in regards to the above subject is very true…we stay in kavalbysandra of RTnagar, there is also a big rajakaluva works the being couple of years back…starting from D.J.halli, shadabnagar, Nagamma layout, oil factory road, MM layout, till Ambedkar college…but never completed till date….the money of bbmp is swolled as usall by contractors…there work is still incomplete…

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Explainer: Tax-zones, Bhu-Aadhaar and other BBMP property tax guidelines

A guide to the BBMP property tax assessment, currently underway. Know more about the process challenges and updates for 2024-25.

Every year, the Bruhat Bengaluru Mahanagara Palike (BBMP) collects property tax during the months of April and May, and a 5% rebate is accorded to encourage timely tax payments. This year, however, BBMP has extended the 5% rebate period for property tax payments until July 31, 2024. If you are a property owner in Bengaluru, you can take advantage of this extended rebate period to pay your property tax before the deadline. One of the reasons for the extension, beyond the regular deadline of April 30th, is the Lok Sabha Elections. According to a circular issued by BBMP Chief Commissioner…

Similar Story

Missing names and missed opportunities: A Chennai citizen’s experience of elections

Irregularities in electoral rolls and voter enrollment in Chennai left many citizens high and dry, while ECI officials looked the other way.

The way the first phase of the 2024 Lok Sabha elections was conducted in Tamil Nadu, especially in Chennai, has laid bare the lacunae in the system. For residents, who were not able to cast their votes despite having valid Voter ID cards, it seemed nothing short of a sham. Every time before the elections, the electoral rolls are updated by Election Commission of India (ECI) officials. Instead of deputing people who are working full-time within the ECI, the work is outsourced to government employees drawn from schools, colleges or other agencies. These ECI staff, who come from distant locations,…