Why Bengaluru areas face chronic power cuts

Overloaded supply and distribution lines and transformers are the reason for load shedding in some of Bengaluru’s areas.

Load shedding, the most dreaded word in summer isn’t always because of power shortage. Most of it has got to do with overloaded distribution and supply lines. Here are some areas where BESCOM has identified issues and proposed solutions. This might help reduce power cuts in Bengaluru.

BESCOM North

♦ There is load shedding in Platinum City, Yelahanka and Sahakaranagara as the cable size is small. The cables are overloaded and they can take maximum power of 40 MW only. The cable size has to be increased from these areas up to the sub-stations

♦ Byadarahalli MUSS and its lines are overloaded causing unscheduled load shedding in areas under the MUSS. A new cable of 4 km length is being laid from Brindavan to Byadarahalli. Another line of 12 km length is being laid to connect Vrushabhavati MUSS to Byadarhalli through Sir MV Layout.

♦ Current Transformers have to be replaced in Vijayanagar and Chandra layout sub stations

♦ In Rajarajeshwari nagar MUSS, two power transformers have to be upgraded from 20 MVA (Million Volt Ampere) to 31.5 MVA

♦ The incoming power lines of LR Bunde MUSS is undersized; power transformers are overloaded. The lines have to be upgraded and two transformers have to be upgraded from 20 MVA to 31.5 MVA

BESCOM South

♦ The 66 KV cable which runs between Hoody and Kadugodi is overloaded. The cable has to be replaced along its entire length of 5.17 kms from EPIP to Kadugodi. Tender has been completed.

♦ The 66 KV cables coming from Hoody Master Unit Sub Station (MUSS) is overloaded for about 500 metres at the Brigade Metropolis apartment complex premises in Whitefield. Currently ITI and NGEF MUSS are supporting the load here. If the cable size is increased, this will no longer be needed.

♦ Areas under HBR and LR Bunde stations have load shedding now as the HBR MUSS is drawing only 66 KV power from Hebbal MUSS. The other source of power for HBR is the 220 KV line from Malur, which is far. Detailed Project Report (DPR) has been approved for laying cable between BIAL and Vidhyanagar. Once this is complete, this circuit can be extended between HBR and Hebbal; a 220 KV line can be drawn from Hebbal to HBR to solve the load shedding problem.

BESCOM Rural

♦ Hoskote New MUSS is drawing power from Malur MUSS through a 66 KV line. The circuit is overloaded and the maximum load possible is 30 MW. This is affecting power supply in HSR, Grindwell and Vidyanagar areas. Another 66 KV line will be drawn from Old Hoskote MUSS to New Hoskote MUSS, to supply power. But there are objections from public against digging the land for installation.

♦ In Devanahalli MUSS, both power transformers are overloaded, causing unscheduled load shedding. A third transformer is required to avoid this.

♦ In Kanakapura MUSS, a transformer is overloaded. Additional transformer has be to installed.

♦ In Jigani MUSS, all three 20 MVA transformers are overloaded and power is shut down for three hours daily to prevent overload. To avoid this, a new MUSS is being constructed, but has been delayed due to public objections. There are plans to replace two of the existing transformers with 31.5 MVA transformers which are already available. The third existing transformer will be replaced with a 31.5 MVA transformer later.

In Attibele, one of the two transformers are overloaded, causing load shedding. It has to be upgraded to a higher capacity transformer. The other transformer, which has a 12.1 KV voltage transformer, is causing high voltage problems to industrial consumers on holidays and Sundays. This has to be replaced with 11 KV transformer (11 KV is the norm). Earlier, when the number of sub stations was lesser, Bangalore had low voltage issues. Now that there are more stations, low voltage issues do not exist and hence high voltage transformers are not needed.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Explainer: Tax-zones, Bhu-Aadhaar and other BBMP property tax guidelines

A guide to the BBMP property tax assessment, currently underway. Know more about the process challenges and updates for 2024-25.

Every year, the Bruhat Bengaluru Mahanagara Palike (BBMP) collects property tax during the months of April and May, and a 5% rebate is accorded to encourage timely tax payments. This year, however, BBMP has extended the 5% rebate period for property tax payments until July 31, 2024. If you are a property owner in Bengaluru, you can take advantage of this extended rebate period to pay your property tax before the deadline. One of the reasons for the extension, beyond the regular deadline of April 30th, is the Lok Sabha Elections. According to a circular issued by BBMP Chief Commissioner…

Similar Story

Missing names and missed opportunities: A Chennai citizen’s experience of elections

Irregularities in electoral rolls and voter enrollment in Chennai left many citizens high and dry, while ECI officials looked the other way.

The way the first phase of the 2024 Lok Sabha elections was conducted in Tamil Nadu, especially in Chennai, has laid bare the lacunae in the system. For residents, who were not able to cast their votes despite having valid Voter ID cards, it seemed nothing short of a sham. Every time before the elections, the electoral rolls are updated by Election Commission of India (ECI) officials. Instead of deputing people who are working full-time within the ECI, the work is outsourced to government employees drawn from schools, colleges or other agencies. These ECI staff, who come from distant locations,…