Drain work submerges quality of life

If a development project on a single road could completely destroy quality of life for residents, it must be this one: BBMP's project at JP Nagar's Puttenahalli Main Road.

The problems of JP Nagar do not end with the underpass mess on the 24th Main, 15th Cross, in fact the residents are facing inconvenience even because of another major construction in that area. This time it is the construction of the drain line that is the cause of concern for the residents.

Compound wall Passway, JP Nagar, Bengalooru

Compound walls broken down and used as pass ways (Pic: Supriya Khandekar)

"There is a fight for getting daily necessities, reaching the grocery shop or the bus stand is a big task. The vegetable vendors also do not come regularly," says Sujatha M, who also lives on one side of the dug up road. She is a housewife and a mother of two kids, she also explained that the dust and noise add to the problem caused due to the digging. Along with her all the residents living in the area remain clueless about the completion dates for the project as there is no board mentioning such details.

The Puttenahalli main road (which leads to the Puttenahalli lake) has been dug up. The whole road is seeing the construction of an underground drain that connects to the Puttenahalli lake. The drain line there is under construction from the past few months.

People living on the either side of the main road find it difficult to reach the other side. In fact walking on the main road itself is next to impossible. Vehicles cannot come that way, if anyone wants to be on the main road then walking is the only way. While even walking is not that easy. One has to use the broken compound walls of the houses on the either side of the road as a passage to reach the desired location.

Construction reached on either side of the houses, JP Nagar, Bangalore

Construction has reached the houses on the either side of the road (Pic: Supriya Khandekar)

The dug up road that has left only mud, water, huge construction material, trucks and cranes all over the place. The digging has reached the houses on the either side of the road and most people have vacated the place. Others however are using these vacant houses by making ways from their compounds and even breaking down the compound walls.

While one side of the road has been temporarily cemented it does not look strong to bear the monsoon. Even on these places the rain water has entered the nearby houses. Along with that the same road has one private clinic still running and the patients have to sit just next to the dust and mud of the construction work.

Even patients on the other side of the road cannot reach the clinic. The whole area flooded because of the rains the earlier night. Some people expressed similar concern about not able to reach the nearest doctor. There are two play schools as well where kids cannot reach.

Clinic near construction, JP Nagar, Bengaluru

S Suresh, in his early forties, stays on the side which is now temporarily cemented. He said, "It took four months for this side to get a temporary road but that side seems to be taking longer due to the rains. There is no other way to walk on this road but to break the compound walls. Even doing that does not work if the place is flooded."

The people who are working on the project are also equally affected by this. Nagarjuna who works on the site said that it is sad to look at people who cannot move around, while he adds that because of monsoon the work will take longer to finish.

Dug up road for drain line, JP Nagar, Bengalooru

Dug up road for drain line (Pic: Supriya Khandekar)

"We stop working in the evening and after a heavy shower we cannot start till late the next day as the whole place is flooded," he explains. Nagarjuna has come from Andhra Pradesh and stays in a temporary blue plastic sheet tent on the site itself. His wife also works on the same site and his two daughters play around.

The BBMP engineer-in-chief AK Gopalaswamy was not available for comment after repeated attempts.

Addendum
On 24 July, Chikkarayappa, Chief Engineer (SWD), BBMP said that the construction will be complete by September this year.

Comments:

  1. Deepa Mohan says:

    Well-written article, Supriya! good description of the immense hardships citizens have to face.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Mumbai Buzz: Heat wave hits Mumbai, BMC starts removing decorative lights from trees… and more

Other news in Mumbai: Fake mark sheets sold online; Barfiwala flyover and Gokhale bridge to be connected; Former Mayor gets anticipatory bail

Heat wave in Mumbai Mumbaikars experienced the hottest day in April in the past decade on Tuesday with the temperatures crossing a scorching 39.7 degree Celsius. According to the Indian Meteorological Department's (IMD) Santacruz observatory, Monday night was also the hottest night of the year in Mumbai. An orange 'severe heatwave' alert was sounded by the IMD for Tuesday. Tuesday's temperature showed an abnormal increase of 6.5 degrees above normal. Night temperatures on Monday also left Mumbaikars sweating with temperatures settling above 27 degrees at Colaba and Santacruz. The heatwave warning was extended to Wednesday with a yellow heatwave alert…

Similar Story

Bengaluru Buzz: Water supply upgrade | KIA gets global awards… and more

Other news of the week: BWSSB may get water from pumping stations, drive to ease traffic congestion and police dispose of 918 abandoned vehicles.

Water supply upgrade Even as the city completes 140 dry days with little rainfall, due to the El Nino effect, the India Meteorological Department (IMD) expects light to moderate showers this month. On April 19th, there were moderate rains. At 37.2 degrees Celsius, April 2nd was the fourth highest temperature for the month recorded in the last 15 years. On March 17th, the Bangalore Water Supply and Sewerage Board (BWSSB) agreed to supply Cauvery water to 21 IT parks in and around Mahadevapura, the BWSSB Chairman said after a meeting with members of the Outer Ring Road Companies Association (ORRCA).…