BBMP’s deadline to fill potholes passes, quietly

Corporators and engineers say there are too many potholes, too little money and too little time. Did the Commissioner speak too soon?

On September 1st 2010, local daily newspapers reported that BBMP Commissioner H Siddaiah had issued a circular to zonal joint commissioners to fill all potholes in the city within a fortnight. Each ward was given Rs 1 lakh for this purpose.

potholes

On September 15th, the deadline came. And went. But potholes continue to remain.

In south Bangalore’s Kengeri (Ward 159), Corporator R Anjanappa (BJP) says they have completed work only to an extent. "Rs 1 lakh is too little money for us to fill all potholes…there are still many potholes to be filled", he says.

Suresh Devathraj, an engineer in the same ward, says they would try to finish filling potholes by next week.

Panning east, the situation is entirely different in Garudacharpalya (Ward 82) in Mahadevapura Assembly Constituency. "No work has been started here. The funds allotted by BBMP have been withdrawn and they are in the process of issuing tenders now for filling potholes, so there is no question of deadline of 15 days", claims corporator N Pillappa (Congress).

However, BBMP Mayor S K Nataraj denies withdrawing funds and says the ward Assistant Executive Engineers (AEE) are responsible to monitor complete the work.

The BBMP Commissioner may have given his directive to fill all potholes in the city in 15 days, but local engineers and corporators explain the practical problems they face while implementing the work, clearly indicating that a 15-day ultimatum may not necessarily work to make the city pothole-free.

K R Puram AEE, Narayan K says they are still in the process of "identifying" potholes. "We are currently working in Devasandra area and the funds allotted are far too small. We will try to finish the work in another ten days and request more funds later. We could not deliver on time due to rain which is worsening the roads further with more potholes", he says.

BBMP Joint Commissioner (Mahadevapura zone) Shivabasavaiah says filling of potholes is a continuous process. "There are a large number of potholes. Our engineers keep looking for them and filling them", he says, adding, "A drive like this will not fill all potholes. Tomorrow rains will come and more potholes will be created."

Comments:

  1. S Srinivasan says:

    The filling of potholes should have been done carefully and professionally. What we see is just dump some demolished structural remains, not tamped properly and Tar mix spread over. This cannot stand even one rain. When vehicles pass over this area, the potholes open up again. In addition to the unscientific speed breaker humps, we have this bonus depressions in the roads to slow down the traffic. This type of shoddy work left to the contractor without any inspection is a waste of public funds. What else we can expect from BBMP. CM does not have his house in all the roads .Afterall, the burden and sufferings are reserved for the general public.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Pedals of change: Chennai’s shift to a sustainable mobility future

Prioritising bicycles over cars and promoting the use of public transport can increase Chennai's sustainability quotient.

The transformation of Chennai, from a trading post entrenched in the bylanes of Fort St. George, to a bustling metropolis with gleaming skyscrapers along the historic Mahabalipuram road underscores its economic progress and growth. The visionaries of the city exhibited exemplary foresight in establishing an extensive road network and suburban train systems that set a precedent for the future. The city’s continued investment in the Metro Rail, connecting important nodes of the city, is encouraging use of public transport. As per the Ease of Moving Index — Chennai City Profile report, Chennai leads the way with the highest mass transit…

Similar Story

ORR-Sarjapura gridlock: Govt, IT sector, commuters must collaborate for solutions

About 7 lakh commute to ORR-Bellandur; between 75,000 and 1 lakh live on and around Sarjapura, facing transport and infrastructure challenges.

The traffic congestion at Outer Ring Road (ORR)-Sarjapura Road has been a long-standing issue. To address this, Citizen Matters held a panel discussion, ‘Solving Sarjapura-ORR Gridlock’ on February 26th. Moderated by Meera K, co-founder of Citizen Matters, the panel included G T Prabhakar Reddy, Chief Traffic Manager, BMTC; Vivekanand Kotikalapudi, Urban Mobility Advisor; Mukund Kumar, Managing Trustee, Iblur Environs Trust; and Srinivas Alavilli, Fellow- Integrated Transport and Road Safety, WRI India.  Sarjapura Road is an integral connection to the IT corridor of south-east Bengaluru. ORR is completely developed with a focus on tech parks. There is currently a surge in…