Air gives way to steel, finally

The ramps of the Whitefield-Kadugodi railway overbridge which were hanging in the air for years have been united by a steel girder on March 26th and 27th.

The wait is almost over – after years of staring at the ramps of the Whitefield-Kadugodi railway bridge that went nowhere, we are happy to report that the first piece of steel girder over the rail lines was put in place at 1.30 am on March 26th, 2010.

Whitefield overbridge

The sandblasted and painted steel girder section installed across the ramps, above the
electrical lines. Pic: Satinder Randhawa.

The work of placing the steel girder over the Whitefield Railway overbridge started just past midnight after the electric lines were disconnected from mains over most of the tracks. Two tracks on the Sai Baba ashram side were still operational. A huge crane was brought in and locked the girder in place at around 12.30 am. The crane did a dry run – turning a full 360 degrees with its lifting arm fully extended to ensure that it did not damage any electric lines.

A big truck brought the first piece of the steel girder (16 m long) along the crane and then the actual work started. The huge steel girder was hoisted up, turned, expertly guided between the electric lines and placed safely in its designated place. The entire operation was beautifully orchestrated by a crew of around 50 people from South Western Railways and the contractor.

Citizen Matters has chronicled this saga over several stories since 2008. (See here and here).

It sounds simple, but considering the weight that the crane was carrying and the narrow distance between the 25 kilovolt electric lines – this thing should have been telecast on Discovery Channel.

The site engineer South Western Railways shared some information with us – here a brief of what we learned :

– There will be two steel girders laid over the railway tracks. Each girder will be 42 m long.

– Each girder will have three pieces, two pieces of 16 m each (these start from the end of the ramps) and a middle piece of 10 m.

– The plan was to put the first 16 m piece (Kadugodi side) and the middle ( 10 m ) piece in place on March 26th midnight, and on March 27th night, the third which is 16 m piece (Hoskote/Sai Baba Ashram side). (At the time this article went live, all three pieces are in place as per plan)

– Once all three pieces are in place they will be welded and riveted together.

– Once this monolith is ready, it will be shifted by a few meters (parallel to it’s current position), so that the temporary support structure can be used to assemble the second girder.

– Once both the long 42m girders are in place – they will be cross-connected with more steel and a steel sheet will be laid over them and which will form the base of the road that will be laid over the girder.

N Kumar, Manging Partner of KPR said that school buses can go over the bridge. The bridge is designed to widstand a load of 200 tons.  ⊕

RELATED
RELATED

Related Articles

Whitefield Bridge begins three month-countdown

Comments:

  1. Maragathavalli Inbamuthiah says:

    It is such a relief to see work finally happening here. Makes it worth it to grin and bear the detour that is longer and slower.

  2. B Dutta says:

    Love the title of the article 😀

  3. Niranjan Raju says:

    At last…Hurray. I have bought a flat on the Sai Baba Ashram-Hoskote side, which will be ready in July 2010. So by the time I shift, the bridge will be ready and functional. I have to take the detour which is OK…except for 2 huge speed bumps near the MVJ COE. My Santro takes a beating everytime on this eventhough I have tried all tricks…Only thing left to do is to carry the car on my shoulders across this bump

    Thanks BLR CitizenMatters for following up closely on this. Maybe you could do something for this speed bump too?

  4. Suresh Mahadevan says:

    Does anyone has any idea when the Whitefield-Kadugodi railway overbridge will be open ?

  5. Venkatesh says:

    Please…Please …Please… Could someone post the latest status on the bridge work. Eagerly awaiting for flyover bridge to be over.

    Thanks,
    Venki

  6. Subramaniam Vincent says:

    Please use this article for tuning into updates. The latest is always posted there.

    http://bangalore.citizenmatters.in/articles/view/1829-overdue-whitefield-bridge-construction-begins

    You can also follow our twitter feed http://www.twitter.com/citizenmatters – we will be updating that regularly from this month.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Pedals of change: Chennai’s shift to a sustainable mobility future

Prioritising bicycles over cars and promoting the use of public transport can increase Chennai's sustainability quotient.

The transformation of Chennai, from a trading post entrenched in the bylanes of Fort St. George, to a bustling metropolis with gleaming skyscrapers along the historic Mahabalipuram road underscores its economic progress and growth. The visionaries of the city exhibited exemplary foresight in establishing an extensive road network and suburban train systems that set a precedent for the future. The city’s continued investment in the Metro Rail, connecting important nodes of the city, is encouraging use of public transport. As per the Ease of Moving Index — Chennai City Profile report, Chennai leads the way with the highest mass transit…

Similar Story

ORR-Sarjapura gridlock: Govt, IT sector, commuters must collaborate for solutions

About 7 lakh commute to ORR-Bellandur; between 75,000 and 1 lakh live on and around Sarjapura, facing transport and infrastructure challenges.

The traffic congestion at Outer Ring Road (ORR)-Sarjapura Road has been a long-standing issue. To address this, Citizen Matters held a panel discussion, ‘Solving Sarjapura-ORR Gridlock’ on February 26th. Moderated by Meera K, co-founder of Citizen Matters, the panel included G T Prabhakar Reddy, Chief Traffic Manager, BMTC; Vivekanand Kotikalapudi, Urban Mobility Advisor; Mukund Kumar, Managing Trustee, Iblur Environs Trust; and Srinivas Alavilli, Fellow- Integrated Transport and Road Safety, WRI India.  Sarjapura Road is an integral connection to the IT corridor of south-east Bengaluru. ORR is completely developed with a focus on tech parks. There is currently a surge in…