Why BBMP’s stormwater drain encroachment clearance drive is delayed

After the 2016 floods, BBMP started the demolition drive to clear drain encroachments, and followed it with a plan to remodel Bengaluru’s stormwater drains. Why is this still not complete?

Following the heavy floods in parts of Bengaluru last monsoon, the Bruhat Bengaluru Mahanagara Palike (BBMP) took up the task of stormwater drain (SWD) encroachment clearance drive in August, 2016.

It has been a year – the drive started in all earnestness but soon got stuck, because of interventions by affected parties and courts. Of course the system was designed to aid all these interventions.

To identify encroachments, BBMP used 50-year-old village maps, as there were no new authentic surveys done in last five decades.But while sanctioning the building plans near stormwater drains, BBMP never had the habit of checking any village maps or master plans. This put the onus of aiding irregularities on BBMP itself. This also gave an easy escape route for encroachers. BBMP, BDA contributed to drain encroachment mess in their own way adding to the confusion.

Stormwater drain saga in Bengaluru is long and eventful. There have been many efforts to remodel storm water drains in the past, and the money has just gone down the drain.

The most important of all is the siphoning off the JnNURM funds in the name of stormwater drain remodeling, for other works. Storm water drains leading to the Koramangala-Challaghatta, Vrushabhavathi and Hebbal Valley received JNNURM funds for remodeling and revival. But the money was diverted for works such as renovating the office of the Chief Engineer – SWD. This article on Deccan Herald explains the details. Comptroller and Auditor General of India (CAG) in the audit report released in June 2013, pointed out the irregularity.

In the aftermath of the floods last year, the government announced in the budget presented in February 2017 that SWDs will be remodelled at a cost of Rs 800 crore to prevent floods.  In May 2017, Chief Minister Siddaramaiah laid the foundation for the remodeling of 192 km of stormwater drains in the city at Laggere. Deccan Herald reported:

These drains are connected to the four valleys of Bengaluru namely, Challaghatta, Hebbal, Koramangala and Vrushabhavathi. The BBMP will construct 192 km of concrete drains at a cost of Rs 800 crore. Under the project, RCC box drain, RCC ‘U’-shaped retaining wall and 19 RCC culverts will be constructed.

Thus the government intended to remodel the drains for which JnNURM funds were sought earlier but diverted elsewhere.  The tendering process saw its own scams, with people not qualified to bid submitting forged certificates and winning the tender, and finally being caught. The tender was cancelled and BBMP called for fresh tenders in August 2017.

728 encroachments await demolition

This year again the city witnessed floods, though comparatively less in magnitude. Localities like Madiwala and Kodichikkanahalli, that were flooded last year and SWD encroachment was cleared, did not report flooding during the recent rains.

But the encroachments too have not been fully cleared. According to the data available at the office of the SWD, of the total 1,953 SWD encroachments identified in BBMP limits, 1,225 encroachments have been cleared and 728 are pending for clearance.

Shivaprasad, Technical Assistant at the SWD section attributes the delay in demolition and clearance on the lack of availability of surveyors. “When we were in the process of surveying and clearing the encroachments, we faced the problem of shortage of surveyors. The office of the Joint Director of Land Records (JDLR) withdrew their services. But with the recent announcements made by the BBMP of restarting the encroachment clearance, we are hopeful that JDLR will depute surveyors for the purpose. And soon we can resume the encroachment clearance drive,” he says.

Then what happened to the 800 crore project to revive the SWDs? Will the SWDs in Bengaluru ever see a makeover?

Storm water drain remodeling under progress officially

Officials say that a total of 408 works are taken up under Rs 800 crore project. It apparently took seven-eight months for the BBMP to get the Detailed Project Report (DPR) ready and then call for tender and finally give the work order in last March/April. They claim that the work of reconstructing and laying SWDs is under progress.

Going by the figures that the BBMP shares, 369 works are taken up in six packages at a project cost of Rs 671 crore. “Work has started in all packages except package 2. The remaining package too has been finalised and the work order will be given soon,” according to Shivaprasad.

Another Rs 26.4 crore will be spent on maintenance work of existing SWDs. Some 30 works which were sanctioned in the past did not see the light of the day apparently due to lack of funds. These works too are expected to be completed using the remaining amount in Rs 800 crore.

Shivaprasad says 40 percent of the total 408 works have commenced and the remaining works too are expected to commence soon. The information related to all the works are available here.

According to the BBMP, the works are likely to be completed by December 2018 as that is the deadline set for the contractors. But will the works actually complete on time and will the storm water drain system in Bengaluru get a facelift? One has to wait and see.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Lok Sabha 2024: Know your MP — Rajan Vichare, Thane

Two time MP Rajan Vichare is contesting for the third time from Thane, with infrastructure development as his election pitch.

Name: Rajan Vichare Constituency: Thane Rajan Baburao Vichare, 63, has been an intrinsic part of Thane becoming a political stronghold of the Shiv Sena. Vichare rose from the party ranks from being a local unit leader (shakha pramukh) of the Shiv Sena to corporator for four terms in the Thane Municipal Corporation (TMC) between 1992 and 2014. He also served as the mayor of Thane from 2007 to 2010.  Subsequently, he represented Thane in the legislature and in Parliament. He has been a member of Parliament (MP) from Thane for two terms in 2014 and 2019 and is now fighting…

Similar Story

‘Malleable, uncertain but determined to vote:’ Thoughts of a first-time voter from Mumbai

As Mumbai gears up for elections, a first-time voter writes about her engagement with politics and expectations from elected representatives.

Voting in the largest democracy in the world holds great responsibility. The moment you press a button on the ballot, you become a part of those who choose to take the onus of moving their country forward. This election will be my first as a voter. In a democracy every citizen has a say in the governance of the nation. But 1.44 billion people cannot all be directly a part of the government. So we choose a few people, who will represent us and our interests— expecting them to meet the needs of the many. As a child, my knowledge about…