Work on Meistripalya Kere starts, to finish by early 2014

After years of litigation and delay, BDA is starting the re-development of Meistripalya Lake in the heart of Koramangala.

Several years of efforts by Koramangala citizens bore fruit on Friday, 12-July-2013 when a Bhoomi Puja was held to mark the start of re-development work on Meistripalya Lake in Koramangala.

Bhoomi puja for Meistripalya Lake re-development, by BTM Layout MLA Ramalinga Reddy, Koramangala corporator Kokila Radhakrishna and other officials. Pic: Srinivas

The work, estimated to cost Rs 175 lakhs, is based on a  Detailed Project Report (DPR), developed by the BDA and Lake Development Authority using inputs furnished by Koramangala citizens. Over the years, a number of elected representatives and officials have played a major role in bringing the project to fruition.

The 11 acre Mestripalya lake bed was embroiled in litigation between the BDA and a litigant who claimed ownership rights over it. In the early 80s the government had acquired vast tracts of land in Koramangala, including the Meistripalya Kere, that happened to be a public tank.  The lake itself was not ‘acquired’, in that sense, but the original owner claimed that the land was his, and went to court to reclaim it.

It was a group of active citizens of Koramangala who took the initiative to move the Supreme Court in the matter — it was a great victory for the citizens of Koramangala when the Supreme Court ruled in 2010 that the BDA would be the owner of the land and the land be protected as an open space and developed as a lake. The Laxman Rau Committee report of 1986 had already declared that the breached tank bed should be developed as a Forest area.

Meistripalya topology map

Meistripalya mentioned in the Survey of India topology map, 1970-71

After the legal victory, the role of the citizens did not end. A group of Koramangala residents got together a group of technical experts to make a detailed plan on how to rejuvenate the lake. The technical group included Dr. Harini Nagendra,  Urban Ecologist, Dr. S Subramanya, Entomologist & Ornithologist, Rohit Marol,  Landscape Architect, Ramesh Sivaram, Environmental Engineer, Manvel Alur, Environmental Specialist, Manjunath, Socio Economic Analyst, and Muralidhar Rao, Coordinator. They worked closely with the Lake Development Authority and BDA which brought out the final DPR.

Though the DPR was ready a year and a half ago, the execution could not proceed till now, as the land survey had to be first completed by the revenue department  

Rajeev Chandrashekar, MP was instrumental in opening the doors of the bureaucracy in BDA and enabling a strong citizen participation in the technical, environmental and sociological aspects of the Mestrikere restoration project. Former BDA and BBMP commissioner, H Siddhiah also played a major role in easing the roadblocks to the project at different points of time.

With all the plans in place now, the lake should have sufficient water for 365 days in the year. Plans are also in place to build a waste water treatment plant to treat the sewage, build a tree arboreum and encourage a sunbird corner.

The Bhoomi Puja function was inaugurated by Ramalinga Reddy, Minister for Transportation, Government of Karnataka in the presence of Kokila Radhakrishna, Corporator, Ward 151, Nayak, BDA Engineer from BDA, and other officials from the BBMP, BWSSB and BDA.

Talking to the residents, Ramalinga Reddy promised that the development work would be completed in a timely manner. Nayak mentioned that they plan to complete work in 9 months.

Residents hope to see the work moving ahead in the next few months with BWSSB’s task being moving sewage lines, BDA’s responsibility for civil works and BBMP taking care of drains and water channels.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Vote for clean air, water security and nature conservation: Environment and civil society groups

The youth of the country will bear the brunt of climate change impact in the absence of government action, say voluntary groups.

The country is going to the polls in one of the most keenly watched elections of all time, and a collective of 70 environment and civil society organisations have appealed to voters to assess the threat to the environment and ecology when they cast their votes in the Lok Sabha 2024 elections. Here is what the organisations have said in a joint statement: As Indians prepare to vote in the Lok Sabha elections this year, it is very important to think of the future of our democracy, especially the youth and their right to clean air and water security in…

Similar Story

Sanjay Van saga: Forest or park, what does Delhi need?

Rich in biodiversity, Sanjay Van in Delhi is a notified reserved forest. Here's why environmentalists fear it may soon be a thing of the past.

The Delhi Forest Department has officially notified the Delhi Development Authority (DDA) about reported tree cutting activities at Sanjay Van. The forest department's south division has verified the claim, citing an infringement of the Delhi Preservation of Trees Act (DPTA) 1994, due to the unauthorised felling of trees in Sanjay Van, Mehrauli, New Delhi. According to officials, the alleged incident came to light through the vigilance of environmental activists. The accusations stemmed from a volunteer organisation called "There is No Earth B," which conducts regular cleanup campaigns at Sanjay Van. With a volunteer base exceeding 1,500 individuals, the group engages…