Stop Bellandur SEZ project, Lake Authority tells KIADB

Following media reports on violation of environment laws, the Lake Development Authority inspected Bengaluru's controversial SEZ project off Bellandur Lake and asked KIADB to stop the construction.

Construction activities continue to encroach the drain coming from Madivala valley that leads to Bellandur lake. Pic: Nikita Malusare

There seems to be no end to controversies surrounding the Bellandur SEZ project opposite Agara Lake near Koramangala, Bengaluru. Karnataka’s Lake Development Authority (LDA), which conducted an inspection recently following media reports, has asked KIADB to stop construction activities on Bellandur lake catchment area by Manipal ETA Infotech Ltd.

The LDA is a governmental body working for the regeneration and conservation of lakes in and around Bangalore city within BMRDA jurisdiction.

Based on the report of the inspection held on June 12th, 2013, Chief Executive Officer of LDA Ravi Ralph wrote to Karnataka Industrial Areas Development Board (KIADB) asking them to stop construction activities and re-classify and maintain the area as Non- SEZ zone or a sensitive zone.

The inspection report by LDA clearly mentioned that such a construction will have an adverse effect on the water which flows to Bellandur lake.

Findings of LDA report

On the orders of the LDA CEO Ravi Ralph, Executive Engineer S R Nagaraj and Assistant Executive Engineer C Nagesh Rao inspected the catchment areas of Bellandur lake where construction of Manipal ETA Infotech is proposed, on June 12th, 2013.

This drain in the Madivala valley channels excess water from Agara area to Jakkasandra area and finally to Bellandur lake.

At the time of inspection, the storm water drain was found to be constructed for about a length of around 150 to 200 metres after which the drain is left open and is not lined.

The width of the drain has been reduced at this juncture and construction debris has been dumped due to huge developmental activities beside the drain. This has restricted the flow of water into Bellandur lake, remarked the inspectors.

The reported concluded stating that “the huge construction activities in this catchment area have resulted in change of land use and directly impacting the catchment of Bellandur lake.”

The Lake Development Authority, in turn, wrote to KIADB requesting to stop the construction activity. “In effect, the said area should be classified and maintained as sensitive area,” said the letter.

KIADB puts the onus back on Manipal ETA

Following the letter, KIADB has asked Manipal ETA Infotech to seek necessary approval from LDA and Karnataka State Pollution Control Board (KSPCB) before continuing any construction activities.

KIADB also directed Manipal ETA Infotech Ltd to seek approval of State High Level Clearance Committee –

  • For change of name of the company from M/s Manipal ETA Infotech Ltd. To M/s Mantri Tech Zone Pvt Ltd,

  • To extend their time period for implementation of the project.

Manipal ETA Infotech seeks approval from LDA

In response to all these letters, Manipal ETA Infotech Ltd. wrote to CEO of LDA on august 31, 2013, justifying the work being done. The proposed project in no way will affect the Storm Water Drain as they have maintained a buffer zone of 30 meters as per zonal regulations, claimed the letter, dthus disputing the inspection report of LDA.

“We are in no way contributing to the reduction of catchment area nor are we playing any role in blocking the storm drain flow and thus impacting Bellandur lake,” says the letter.

Manipal ETA Infotech has already agreed to follow all the conditions laid by the Ecology and Environment Department and accordingly a compliance letter is also sent to Regional Office of the Ministry of Environment and Forests periodically, stated the letter.

The letter claimed to have received approvals from KSPCB and Ministry of Environment and Forests. With this letter, Manipal ETA Infotech has approached the Lake Development Authority (LDA) seeking the necessary approval for the proposed development.

SEZ, or residential-commercial?

Interestingly, the letter said that the land in question was allotted to Manipal ETA Infotech Ltd  by KIADB for residential and commercial developments, and that the development doesn’t dome under SEZ classification.

On the contrary, the State-level Expert Appraisal Committee (SEAC), Karnataka, which had  scrutinised this project in its 67th meeting held on April 8th, 2011, sees the project as a SEZ project. “The proponent and environmental consultant present explained the ToR. The proponent informed that Special Economic Zone (SEZ) is located within the project site and 27 MW cogeneration power plant is also proposed. The SEZ will be treated as a separate unit as per SEZ norms,” the report said.

Copies of all the above letters are with Citizen Matters.

Citizen Matters first broke the story on the environmental issues with the Bellandur SEZ in late March 2013 and since has published several stories. They are:

Rs 2300 cr realty project near K’mangala on, without BWSSB’s knowledge

Agara SEZ to multiply traffic on Sarjapur Road

Mantri’s 72 acre project encroaching Rajakaluve: IISc report

How govt helps SEZ trump Bellandur lake

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Vote for clean air, water security and nature conservation: Environment and civil society groups

The youth of the country will bear the brunt of climate change impact in the absence of government action, say voluntary groups.

The country is going to the polls in one of the most keenly watched elections of all time, and a collective of 70 environment and civil society organisations have appealed to voters to assess the threat to the environment and ecology when they cast their votes in the Lok Sabha 2024 elections. Here is what the organisations have said in a joint statement: As Indians prepare to vote in the Lok Sabha elections this year, it is very important to think of the future of our democracy, especially the youth and their right to clean air and water security in…

Similar Story

Sanjay Van saga: Forest or park, what does Delhi need?

Rich in biodiversity, Sanjay Van in Delhi is a notified reserved forest. Here's why environmentalists fear it may soon be a thing of the past.

The Delhi Forest Department has officially notified the Delhi Development Authority (DDA) about reported tree cutting activities at Sanjay Van. The forest department's south division has verified the claim, citing an infringement of the Delhi Preservation of Trees Act (DPTA) 1994, due to the unauthorised felling of trees in Sanjay Van, Mehrauli, New Delhi. According to officials, the alleged incident came to light through the vigilance of environmental activists. The accusations stemmed from a volunteer organisation called "There is No Earth B," which conducts regular cleanup campaigns at Sanjay Van. With a volunteer base exceeding 1,500 individuals, the group engages…