Why Bengaluru areas face chronic power cuts

Overloaded supply and distribution lines and transformers are the reason for load shedding in some of Bengaluru’s areas.

Load shedding, the most dreaded word in summer isn’t always because of power shortage. Most of it has got to do with overloaded distribution and supply lines. Here are some areas where BESCOM has identified issues and proposed solutions. This might help reduce power cuts in Bengaluru.

BESCOM North

♦ There is load shedding in Platinum City, Yelahanka and Sahakaranagara as the cable size is small. The cables are overloaded and they can take maximum power of 40 MW only. The cable size has to be increased from these areas up to the sub-stations

♦ Byadarahalli MUSS and its lines are overloaded causing unscheduled load shedding in areas under the MUSS. A new cable of 4 km length is being laid from Brindavan to Byadarahalli. Another line of 12 km length is being laid to connect Vrushabhavati MUSS to Byadarhalli through Sir MV Layout.

♦ Current Transformers have to be replaced in Vijayanagar and Chandra layout sub stations

♦ In Rajarajeshwari nagar MUSS, two power transformers have to be upgraded from 20 MVA (Million Volt Ampere) to 31.5 MVA

♦ The incoming power lines of LR Bunde MUSS is undersized; power transformers are overloaded. The lines have to be upgraded and two transformers have to be upgraded from 20 MVA to 31.5 MVA

BESCOM South

♦ The 66 KV cable which runs between Hoody and Kadugodi is overloaded. The cable has to be replaced along its entire length of 5.17 kms from EPIP to Kadugodi. Tender has been completed.

♦ The 66 KV cables coming from Hoody Master Unit Sub Station (MUSS) is overloaded for about 500 metres at the Brigade Metropolis apartment complex premises in Whitefield. Currently ITI and NGEF MUSS are supporting the load here. If the cable size is increased, this will no longer be needed.

♦ Areas under HBR and LR Bunde stations have load shedding now as the HBR MUSS is drawing only 66 KV power from Hebbal MUSS. The other source of power for HBR is the 220 KV line from Malur, which is far. Detailed Project Report (DPR) has been approved for laying cable between BIAL and Vidhyanagar. Once this is complete, this circuit can be extended between HBR and Hebbal; a 220 KV line can be drawn from Hebbal to HBR to solve the load shedding problem.

BESCOM Rural

♦ Hoskote New MUSS is drawing power from Malur MUSS through a 66 KV line. The circuit is overloaded and the maximum load possible is 30 MW. This is affecting power supply in HSR, Grindwell and Vidyanagar areas. Another 66 KV line will be drawn from Old Hoskote MUSS to New Hoskote MUSS, to supply power. But there are objections from public against digging the land for installation.

♦ In Devanahalli MUSS, both power transformers are overloaded, causing unscheduled load shedding. A third transformer is required to avoid this.

♦ In Kanakapura MUSS, a transformer is overloaded. Additional transformer has be to installed.

♦ In Jigani MUSS, all three 20 MVA transformers are overloaded and power is shut down for three hours daily to prevent overload. To avoid this, a new MUSS is being constructed, but has been delayed due to public objections. There are plans to replace two of the existing transformers with 31.5 MVA transformers which are already available. The third existing transformer will be replaced with a 31.5 MVA transformer later.

In Attibele, one of the two transformers are overloaded, causing load shedding. It has to be upgraded to a higher capacity transformer. The other transformer, which has a 12.1 KV voltage transformer, is causing high voltage problems to industrial consumers on holidays and Sundays. This has to be replaced with 11 KV transformer (11 KV is the norm). Earlier, when the number of sub stations was lesser, Bangalore had low voltage issues. Now that there are more stations, low voltage issues do not exist and hence high voltage transformers are not needed.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Need to make Bengaluru a 15-minute city: Rajeev Gowda, Lok Sabha Congress candidate

The Bangalore North INC candidate plans to reduce carbon footprint and build blue-green infrastructure for the city's betterment.

An election campaign in this gruelling summer has been an exhausting exercise even for the most seasoned politicians. Rajeev Gowda, the Congress Party candidate for Bangalore North constituency, admitted as much. But he says, it also highlights the urgency for the measures to combat climate change and his plans for the constituency, should he be elected.  After more than two decades in politics, the former Rajya Sabha MP is all set to fight it out for a Lok Sabha berth for the first time.           We caught up with the former professor of the Indian Institute of Management Bangalore (IIMB) at…

Similar Story

, , ,

Lok Sabha 2024: A people’s manifesto for urban areas

Shehri Rashtriya Andolankari Manch (SHRAM) has released a ‘Shehri Sankalp Patr’ with their collective vision for the marginalised in cities.

Cities in India are set to host half of the population by 2030, driving the country's ‘growth’ and ‘development’. Urbanisation is now being seen as a key focus area of public policy and ‘solution’ to ‘development needs’ of our country. However, this rapid urbanisation has brought numerous challenges, particularly for the urban poor, working class, and informal workers who struggle to access housing, livelihoods, and basic rights like water, healthcare, and education. Despite contributing significantly to cities, their rights have often been ignored and violated until now. Over the past year, community groups, workers’ collectives, and people's movements with decades-long…