New life for works coordination; nascent effort underway

It’s a first for Bengaluru. Stung by criticism, local authorities and the traffic police claim they will now coordinate select public works using a simple one-page agreement.

For years now, Bangaloreans have gotten accustomed to seeing dug up roads across the city. Furthermore, one doesn’t know who has dug it up or why and when it is likely to be closed. And then traffic suffers. The traffic police are clueless about the roadwork and are then forced to divert traffic.

"Sometimes we don’t even know who has dug up the road", points out Praveen Sood, Additional Commissioner of Police (Traffic).  Nothing new in namma Bengaluru. Coordination, or the lack of it has always been a challenge for many local authorities – BBMP, BTP, BWSSB, BDA, BMTC, and so on.

But times are changing and Bangaloreans can now expect some much-required change in the functioning of various agencies. Take the case of a sewerage line being repaired by the BWSSB in Ulsoor, between MEG Gate and Sathyanarayana temple. The water board and traffic police have signed what is called the Public Works Coordination Agreement (PWCA), a first of its kind system introduced in Bengaluru. This is to ensure better coordination between these agencies and divert traffic accordingly.

BBMP/BWSSB work on Hosahalli Main Road, Padarayanapura in Vijaynagar. Traffic has been diverted on this road till December 28th. Pic: Vaishnavi Vittal.

The signatures indicate that the agenices have ‘approved’ the execution of the project, keeping in mind their respective areas of work. It is also a way for them to be aware of the details of such projects.

The state government, under the support of the chief minister’s Agenda for Bengaluru Infrastructure Development (ABIDe) task force, has introduced the PWCA. Dr Ashwin Mahesh, Urban Strategy Advisor for the Government of Karnataka and Member of the ABIDe task force says, “The agreement is between all the city agenices, and they have all agreed to work through this mechanism”. He adds that this was agreed upon at a high-level coordination committee meeting in November, chaired by Dr Ravindra, Advisor to Chief Minister on Urban Affairs and ABIDe task force member.

The agreement though is not mandatory but “a gentlemanly agreement between various agencies under the aegis of ABIDe”, says Sood.

This is a sample copy of the Public Works Coordination Agreement introduced by the state government. Click picture to enlarge.

Mahesh explains that when a road-work project is taken up, say by BBMP, BESCOM, BWSSB or any other civic agency, they should mention the nature of work in this agreement. This should include the date of starting the work and date of possible completion. If say, telephone lines have to be shifted for the project, the executing agency should write to the BSNL asking them to shift the lines.

Likewise, if any other agency is involved, the main executing agency should get a signature from these agencies and then carry out the work. In case of BBMP-related works, the BTP will sign the PWCA last. In case of work to be carried out by other agencies, BBMP will sign last.

In the case of the BWSSB work in Ulsoor, Sood says that the BWSSB has stated that the work will take three and a half months to complete. The start and end dates mentioned in the agreement are November 16th and February 28th, he says. “It will be some kind of a moral binding. Let’s see what happens”.

Sood also cites two more examples where such agreements have been signed. For replacing a sewage pipe on Chinmaya Mission Road in Indiranagar, the BWSSB and traffic police have signed an agreement. As per the PWCA, this work is between November 25th and January 10th, he says. A private company, Tata Communications are laying electric cables on Mahatma Gandhi Road, for which they have signed the agreement along with the BBMP and traffic police. Sood says that the schedule for this work is between December 11th and March 2nd.

The PWCA is to be used only for short-term projects that require cutting of the road and blocking/diversion of traffic. Sood says that for long-term projects like flyovers and underpasses, this agreement will not be used as they require a different kind of traffic management. Neither will it be applied for very short, one-day type works.

Sood also explains that the Bangalore Traffic Police will block or divert traffic only after the executing agency brings their raw material to the site and is ready to begin work. He says that such an agreement is necessary since very often roads are dug up and not restored, or a project is started but not completed.

“Any development affects us. So there is a need for coordination. We (the public) are the biggest beneficiaries”. Sood says that it will take about 15 days for the necessary agencies to sign the agreement.

Mahesh says that the aim of such an agreement is to create a process where each agency is told about the work. It brings about accountability and also gives an opportunity to document everything, he says.

The agreement was to be used for some BBMP/BWSSB work in Vijaynagar. However due to an emergency, work started immediately, prior to signing the agreement. The traffic police have diverted traffic here, in coordination with the BBMP. Pic: Vaishnavi Vittal.

Learning curve

Even as this attempt has been made to bring about coordination, the PWCA has not been used in some cases. It was about to be used for a project on Hosahalli Main Road in Padarayanapura in Vijaynagar, where the BBMP and BWSSB are working on constructing a culvert and repairing pipes respectively. Sood says that this work had to be started immediately as drinking water and sewerage were getting mixed up.

“The PWCA is for projects, not emergencies. The DCP (West) did tell me. But we will get it signed”, he says. This work is scheduled to be completed in 15 days. The traffic police, however, have diverted traffic by not allowing vehicles between Kuvempu Circle and Sangam Circle on Padarayanapura Main Road. This is in force between December 14th and 28th, almost 15 days.

Sood says that coordination always existed between agencies, but it was more on a person-to-person basis. “This is the first time we are documenting this and institutionalising the procedure”.

Sood states another example where this sort of coordination took place without even having to sign an agreement. This was when the BBMP asked the traffic police to divert traffic on Bannerghatta Road, near the marble market, in order for them to close a culvert. “We felt that the road need not be blocked. The work can be carried out without blocking traffic. In the last stage of the work, if necessary, we will block traffic”.

Similarly, he explains the case of some road cutting work that the BBMP wanted to carry out on Marigowda Road near NIMHANS. “Bannerghatta Road and Marigowda Road are parallel. If we block both roads, where will traffic go? So we have told the BBMP to first finish the work on Bannerghatta Road and then do the other”.

Sood feels that such agreements will bring about some much-needed discipline. “The system is getting established. We are going through a learning curve”.  

Comments:

  1. Pramod Naik says:

    Great article. Wonder who the brilliant IAS officer is that leads the BWSSB, who doesn’t know the difference between drinking water pipes and sewage water pipes? It’s taken approximately 60 years for these brilliant IAS and IPS officers to finally realize that they need to coordinate some civic projects!

  2. M V K Anil Kumar says:

    ROAD CUTTING BY SERVICE PROVIDERS

    We had similar experience with Airtel, this year during January 24th, Airtel people wanted lay cables and choose to dig the road @ Ashwini Layout in the night around 10-00 Pm, We immediately contacted the East Control room of BBMP and asked them to stop the work and asked them to wait till the BBMP Officials arrival, but the Airtel people disappeared from the scene and again on 26th January they want to carry out the work, which was again stopped. Some of the Service providers doesn’t have any permission to dig the road, they do the work with some understanding with the ward Officials ignoring the official procedure.

    In October this year when Tata’s started digging the road, We sought the copy of the permission, they shown the approval issued from Duct division of BBMP @ Head office, which was not informed to the Local Engineers. But We had informed the Control room as well as Ward Engineers to cross check the same and they confirmed the same.

    Recently my neighbor wanted to dig the road for change of bore for water supply, he had to shell out around Rs.9,000/- as BBMP official charges for permission to cut the road(30 feet road).

    With regards,
    Anil

  3. Srikanth Parthasarathy says:

    Thanks for the wonderful article. Good to know about the new initiative. Documentation always brings in discipline but i hope this will be followed consistently else this will never sustain. Also knowing start and end dates will be really helpful to track the progress.

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Similar Story

Traffic and mobility in Bengaluru: Plans, reality and what your MP said

PC Mohan has backed the Bengaluru suburban rail network; Tejasvi Surya has also urged for investment in mass rapid transport systems.

Traffic congestion and and mobility are among Bengaluru's topmost concerns today. In the run up to the elections, as the spotlight turns on how the city's sitting MPs have performed over the last five years, their actions and stance on this issue certainly deserves some scrutiny. How have they engaged with the issue? Did they propose any solutions? The major traffic & mobility issues In 2019, Bengaluru recorded the second highest number of vehicle, with over 80 lakh. Nearly 84% of households have motor vehicles. Lack of first and last mile connectivity, reduced bus ridership, under-completion of metro connectivity across…

Similar Story

Pedals of change: Chennai’s shift to a sustainable mobility future

Prioritising bicycles over cars and promoting the use of public transport can increase Chennai's sustainability quotient.

The transformation of Chennai, from a trading post entrenched in the bylanes of Fort St. George, to a bustling metropolis with gleaming skyscrapers along the historic Mahabalipuram road underscores its economic progress and growth. The visionaries of the city exhibited exemplary foresight in establishing an extensive road network and suburban train systems that set a precedent for the future. The city’s continued investment in the Metro Rail, connecting important nodes of the city, is encouraging use of public transport. As per the Ease of Moving Index — Chennai City Profile report, Chennai leads the way with the highest mass transit…